Main Campus Summer 2025 Sewer Repair Project

May 28, 2025

This summer, Real Estate and Property Management will conduct essential repairs to the Main Campus sewer system. Work is scheduled throughout May, June and July.

This project will require temporary closures in a variety of areas across the Main Campus, including roads, sidewalks and loading docks. When roads are closed, flaggers will be present to direct traffic. Closed sidewalks will be cordoned off for safety, with signage in place to direct foot traffic.

When work impacts Chaparral or Laurel Village, individuals staying in these residence halls will need to request building access from Campus Services via email.

Dates

Location

Impact

5/28-6/3

Power & Dynamics Systems Lab

  • Front sidewalk closed

6/4-6/10

Chaparral Village

  • Multiple sidewalk closures
  • Partial road closure on Angelina Way

6/11-6/20

Student Union
Laurel Village

  • Limited access to Student Union loading dock
  • Multiple sidewalk closures around Laurel Village

6/12-7/11

Tennis Courts
Student Union

  • Sidewalk closure

6/23-6/27

UTSA Circle
Main Building/John Peace Library

  • Partial road closure (UTSA Circle)
  • Sidewalk closure

6/30-7/10

Biosciences Building
Engineering Building
Applied Engineering & Technology Building

  • Multiple sidewalk closures

6/30-7/10

Devine Avenue

  • Partial road closure

6/30-7/10

Ximenes Lot

  • Lane and parking space closures

7/11-7/17

Student Union
H-E-B Student Union
Convocation Center
Intercollegiate Athletics Building

  • Multiple sidewalk closures
  • Partial road closures – Devine and Brenan Avenues

Additional information will be provided about these impacts throughout the summer. For questions, please reach out to Real Estate and Property Management.